A crew of 3 workers is budgeted to install 180 m² at a CREW productivity of 30 m² per elapsed working hour. Travel is 1.5 hours per worker for the whole job. Each worker costs $28 per paid hour. Equipment costs $45 per on-site elapsed hour only; materials cost $900. Ignore breaks, overtime and taxes.
Calculate the on-site person-hours. Keep intermediate values unrounded; round the final answer to 4 decimal places if needed.